To provide short-term relief in the certification process, the legal basis for certification — the "Ordinance on the Verification of Electrotechnical Properties of Energy Systems" (NELEV) — was amended in July 2022. During the transition period ending December 31, 2025, plant certificates B can be issued under certain conditions.
To do so, the plant operator or electrical planner must inform the certification body that they are requesting the "plant certificate (B) subject to conditions" procedure in accordance with Section 2(2b) of the NELEV as of July 30, 2022, or Supplement 2 to the FGW TR8 Rev. 09 as of August 24, 2022. All remaining open verification points must be verified within 18 months of commissioning the first generation unit as part of preparing the declaration of conformity (proof of full compliance with VDE-AR-N 4110 requirements).